Monday, December 2, 2109 East Columbia Avenue Construction Update

As of Friday November 29, 2019 the Columbia Ave Sewer project has been delayed up to 2 days. The crew’s experienced a delay in trench excavation on Tuesday of last week and it took extra time as we approached the existing sewer trench.

The upcoming week we foresee a tie in at NE 14th Street by the end of the week. The crews this week are installing sewer mainline in front of these addresses along E. Columbia; 34415, 34403,34391. Sometime on Friday 12/6/19 or Monday 12/9/19 Phase 2 of our traffic control plan will take effect during work hours.

As we move forward installing the sewer line do not forget that interruptions to construction do occur and these weekly updates are critical for awareness. They impact our crew safety and resident planning. Please be aware that the project schedule can change from day to day as we do our best to provide a quality project in a timely manner.

Please be aware of construction activities at all times. This includes and is not limited to pipe crew member, flaggers, company vehicles and large equipment, dump trucks and their trailers and all pedestrian traffic.

Please obey all construction signing especially detour routes and flagger directions. Our flagging personnel are happy to help with any questions you may have.

Please be safe and be aware of our construction workers as they are committed and focused on construction activities.

Thank You and Best Regards,

Jason Turnquist

Assistant Project Manager

Tapani Inc.

Office:360-687-1148