November 25 East Columbia Avenue Construction update

As of Friday November 22, 2019 the Columbia Ave Sewer project has been delayed up to 3 days. A delay due to staking conflicts that ended up stopping work on midday Wednesday and resolving on Friday pushed the schedule back three more days.

The upcoming week is forecasted to be wet at the beginning of the week and cold at the end of the week. Please make sure that you drive slow and alert through the construction zone as rain changes to ice.

As we move forward installing the sewer line do not forget that interruptions to construction do occur and these weekly updates are critical for awareness. They impact our crew safety and resident planning. Please be aware that the project schedule can change from day to day as we do our best to provide a quality project in a timely manner.

Please be aware of construction activities at all times. This includes and is not limited to pipe crew member, flaggers, company vehicles and large equipment, dump trucks and their trailers and all pedestrian traffic.

Please obey all construction signing especially detour routes and flagger directions. Our flagging personnel are happy to help with any questions you may have.

Please be safe and be aware of our construction workers as they are committed and focused on construction activities.

Thank You and Best Regards,

Jason Turnquist

Assistant Project Manager

Tapani Inc.

Office:360-687-1148